Tentative plan


April 16th
• Team charters

April 28th
• Team WBS that includes work and time estimates
• Material and equipment list for the teams work. This list should indicate each item, quantity, type, style, etc. and will be used for budget allocation purposes
• Initial project network
• Financial status report

April 30th
• 1st draft SOW to instructor
• Pre-project plan
• Quality and performance standards and procedures must be proposed – responsibilities, timing of quality checks, means of communicating and resolving quality problems

May 5th
• SOW to class
• Project risk assessment and contingency plans
• Final material and equipment list
• Final quality assurance and safety plans – consolidation and reconciliation of inputs from various work teams
• Financial status report
• Scope adjustment

May 6th
• Project plan presentation – must include responsibility matrix and set up task for each day and project closeout plan
• Make sure everyone knows what they are doing

May 9th-11th
Work the Plan

May 12th
• Status report for work weekend
• Adjustments needed

May 13th
• Project plan update/adjustments for second weekend – must include responsibility matrix and set up task for each day and project closeout plan
• Make sure everyone knows what they are doing for second weekend

May 16th-18th
Work the Plan